Operating procedures functional to the start-up of the “regime phase” of the new balancing of the natural gas system

Taking into account the Decision 66/2017/R/GAS on provisions of the natural-gas market rules functional to the start-up of the balancing regime that:

  • Article 2 provides that 'the transitional provisions for the management of the markets referred to in Article 2 of Decision 312/2016/R/GAS, continue to apply until and no later than 31 March 2017 ";
  • Article 3 provides that "with the execution of transactions concluded in market sessions related to the gas day March 31, 2017 the platform for the balancing referred to in Article 5 of Decision ARG/gas 45/11 shall cease to operate, and the agreement between GME and Snam Rete Gas referred to in paragraph 3.3 of the same agreement shall terminate";
  • Article 4 provides that "GME shall define and publish, well before 31 March 2017, the operating procedures for the implementation of the provisions referred to in section 3";

GME informs that:

  • The new MGAS Rules shall become effective from 1 April 2017, after the closing of the MGS session (11.00 a.m.) and the PB-GAS Regulations shall be simultaneously repealed. It follows that, after that date:
    • PB-GAS shall cease to exist;
    • the existing relationships on the PB-GAS shall not be transferred on the MGAS, neither as regards Participants/Users, nor as regards the offers (in particular, this implies that before April 1 - with the PB-GAS Regulations still in force – no bids/offers referred to 1 April or subsequent days shall be submitted, since at the time of the determination of the results of the MGS relating to those gas days, the PB-GAS Regulations would no longer be in force as "replaced" by the new MGAS Rules);
    • in the MGAS, only Participants and Users admitted/enabled on the MGAS/MP-GAS will be allowed to operate on the MPL and MGS; namely, all Participants and Users currently active on the PB-GAS shall not be allowed to operate on the MPL and MGS unless admitted/enabled on the MGAS/MP-GAS;
  • the switching of systems shall be carried out after the publication of the results of MGS session as of flow date 31 March 2017 (roughly on 1 April 2017 at 11 a.m.) and shall consist of:
    • a records update of the MPL and the MGS, for which all users admitted to MP-GAS shall be authorized to operate;
    • activation of the guarantees building block for MPL and MGS.

 

In order for such business plan to be carried out, the following measures to restrict certain operations are necessary, namely:

  • The switching activities require IT platforms of the MPL and the MGS to be claimed off-line for two hours, as a precaution, on April 1 from 11.00 a.m. to 1.00 p.m. while the MGAS platform, to be claimed off-line for 30 minutes, from 11:00 a.m. to 11:30 a.m.. Simultaneously, bids/offers present on the MGAS platform’s book during the off-line period, will be automatically revoked;
  • The submission of bids/offers on the MGS, which, as provided in the corresponding Technical Rules, is normally permitted starting from 9:00 a.m. of the 4th gas-day preceding the gas day to which the trading refers, shall be limited for the MGAS sessions related to the gas days 1, 2, 3, 4 and 5 April, for which the sitting for the submission will be opened on 1 April at 1:00 p.m


Gestore dei Mercati Energetici S.p.A.
Sole Shareholder: Gestore dei Servizi Energetici - GSE S.p.A., as per art. 5, Legislative Decree 79/99
Company subject to the management and coordination of Gestore dei Servizi Energetici – GSE S.p.A.
Share Capital: € 7,500,000.00 fully paid up
Registered Office - Viale Maresciallo Pilsudski, 122/124, 00197 Rome tel.no. +39-06-80121, fax no. +39-06-80124524, email: info@mercatoelettrico.org
Rome Companies' Register, VAT and Taxpayer's Code: 06208031002 Rome Economic and Administrative Index: 953866